Mumbai Metro Rail Corporation to spend Rs 300 cr to install escalators
26 Jul 2021
2 Min Read
CW Team
MMRC told the media that 414 escalators will be installed between SEEPZ and Colaba. The escalators will have multiple speed options, with the maximum being 0.65 metre per second.
An MMRC officer told the media that two types of escalators would be installed on the complete route, one with a capacity of carrying 6,000 people per hour with a speed of 0.50 metres per second and another with an hourly capacity of 7,300 people at a speed of 0.65 metres per second according to the plan. He added that Rs 292.56 crore is the estimated cost for Metro Line -3 escalators.
The tentative deadline date for the installation work completion for the first prototype escalator is mid-August 2021 at MIDC.
Although the groundwork is in full swing, the car shed location for Metro line 3 has still not been finalised.
MMRC recently achieved its 39th breakthrough at the proposed Mahalaxmi Metro Station. The upline drive of 1117.5 metres has been completed by TBM Tansa-2 from Science Museum Metro Station to Mahalaxmi Metro Station in 257 days, using 745 concrete rings.
The package-3, which includes Mahalaxmi, Acharya Atre Chowk and Worli Metro stations, Science Museum and Mumbai Central, has now witnessed a total of three breakthroughs - Science Museum to Mahalaxmi (upline 1,117.5m) and Science Museum to Worli (upline 2,072m and downline 2,057m) and is the longest stretch of the corridor.
Metro line 3 is an underground corridor running along Colaba-Bandra-SEEPZ, which is 33.5 km long. The length of the corridor is marked with 27 key stations, out of which 26 will be underground.
Also read: Mumbai Metro-3 project faces cash crunch
Also read: Colaba-Bandra-SEEPZ Metro-3 corridor: MMRC achieves 38th breakthrough
MMRC told the media that 414 escalators will be installed between SEEPZ and Colaba. The escalators will have multiple speed options, with the maximum being 0.65 metre per second.
An MMRC officer told the media that two types of escalators would be installed on the complete route, one with a capacity of carrying 6,000 people per hour with a speed of 0.50 metres per second and another with an hourly capacity of 7,300 people at a speed of 0.65 metres per second according to the plan. He added that Rs 292.56 crore is the estimated cost for Metro Line -3 escalators.
The tentative deadline date for the installation work completion for the first prototype escalator is mid-August 2021 at MIDC.
Although the groundwork is in full swing, the car shed location for Metro line 3 has still not been finalised.
MMRC recently achieved its 39th breakthrough at the proposed Mahalaxmi Metro Station. The upline drive of 1117.5 metres has been completed by TBM Tansa-2 from Science Museum Metro Station to Mahalaxmi Metro Station in 257 days, using 745 concrete rings.
The package-3, which includes Mahalaxmi, Acharya Atre Chowk and Worli Metro stations, Science Museum and Mumbai Central, has now witnessed a total of three breakthroughs - Science Museum to Mahalaxmi (upline 1,117.5m) and Science Museum to Worli (upline 2,072m and downline 2,057m) and is the longest stretch of the corridor.
Metro line 3 is an underground corridor running along Colaba-Bandra-SEEPZ, which is 33.5 km long. The length of the corridor is marked with 27 key stations, out of which 26 will be underground.
Image Source
Also read: Mumbai Metro-3 project faces cash crunch
Also read: Colaba-Bandra-SEEPZ Metro-3 corridor: MMRC achieves 38th breakthrough
Next Story
NHAI Limits Engineers to 10 Highway Projects Each
The National Highways Authority of India (NHAI) has announced a new policy restricting consultancy firms to assign no more than 10 national highway projects per engineer for supervision and construction oversight. This rule, intended to enhance monitoring and execution quality, will come into effect 60 days from the date of announcement, allowing firms time to adjust their staffing and assignments.In a statement issued on Thursday, NHAI highlighted concerns that engineers assigned by consultancy firms鈥攁cting as Independent Engineers, Authority Engineers, or Supervision Consultants鈥攚ere oft..
Next Story
Rs 150 Million Cleared to Ease Traffic on Mumbai鈥揋oa Route
To address growing traffic congestion on the Mumbai鈥揋oa National Highway, Maharashtra Deputy Chief Minister Ajit Pawar has approved the redevelopment of four alternate routes. This move comes ahead of the completion of the Indapur and Mangaon bypass roads, with Rs 150 million sanctioned for the immediate upgrades.The four alternative stretches identified for redevelopment are:Morba Road to Mumbai鈥揋oa HighwaySainagar Canal Bridge to Uttekhol Canal VillageNizampur Canal Road to Bhadav Road (within Mangaon Nagar Panchayat)Indapur Canal Road to Wigavli Phata Road on the highwayThe directive wa..
Next Story
Versova-Bandra Sea Link Set for Completion by July 2027
The Versova-Bandra Sea Link (VBSL) is expected to be operational by July 2027, with 25 per cent of the construction work already completed. The Rs 181.2 billion infrastructure project鈥攗p from its original estimate of Rs 113.32 billion鈥攊s steadily advancing despite the complexities of marine engineering.According to Rajesh Patil, Joint Managing Director of the Maharashtra State Road Development Corporation (MSRDC), the initial foundation and pier work is progressing rapidly. While work in the sea will pause during the monsoon, land-based construction, including connectors, will continue thr..