The East Coast Railway (ECoR) has announced that the second-longest railway viaduct in India, currently under construction between Buguda and Banigochha stations as part of the Khurda Road–Balangir new line project, is expected to be completed by August 2026. Spanning 4.77 kilometres, the viaduct includes a tallest pier standing 26 metres high.
The bridge is being built to enhance rail connectivity in Odisha’s interior regions. The project contract was awarded to Rahee Group and is valued at Rs 2.69 billion. The scope includes viaduct construction, major bridges, road overbridges (ROBs), and associated works across a 20-kilometre section between KM 123 and KM 143 of the Buguda–Banigochha stretch.
The viaduct runs from Jamusahi to Gurah village in Nayagarh district and falls between Buguda and Banigochha stations. As of now, 98 foundations, 62 bed blocks, and 41 span girders have been completed.
In addition to this major viaduct, Rahee Group is also constructing ROB No. 229, a composite girder bridge at chainage KM 105.06, located between Nuagaon and Daspalla. The company is also providing construction vehicles, site infrastructure, and auxiliary services required to support the project’s execution.
Shri Rajesh Kumar Das, Deputy Chief Engineer of ECoR, stated that once completed, the viaduct will be second in length only to the Bogibeel Bridge over the Brahmaputra in Assam.
The alignment of the railway had to be altered due to its intersection with the upcoming Brutang irrigation project in Nayagarh district. A substantial part of the railway route was originally set to pass through the planned reservoir. Following consultations with the Odisha Water Resources Department, the alignment was modified to include the 4.77-kilometre viaduct, thereby avoiding disruption to the reservoir infrastructure.
In parallel, another viaduct measuring 1,257.6 metres is under construction in Boudh district as part of the same new line project. Shri Das noted that the 75-kilometre segment between Daspalla and Purunakatak will offer passengers a scenic route, with the viaduct and seven tunnels passing through dense forest regions in Nayagarh and Boudh.
The East Coast Railway (ECoR) has announced that the second-longest railway viaduct in India, currently under construction between Buguda and Banigochha stations as part of the Khurda Road–Balangir new line project, is expected to be completed by August 2026. Spanning 4.77 kilometres, the viaduct includes a tallest pier standing 26 metres high.The bridge is being built to enhance rail connectivity in Odisha’s interior regions. The project contract was awarded to Rahee Group and is valued at Rs 2.69 billion. The scope includes viaduct construction, major bridges, road overbridges (ROBs), and associated works across a 20-kilometre section between KM 123 and KM 143 of the Buguda–Banigochha stretch.The viaduct runs from Jamusahi to Gurah village in Nayagarh district and falls between Buguda and Banigochha stations. As of now, 98 foundations, 62 bed blocks, and 41 span girders have been completed.In addition to this major viaduct, Rahee Group is also constructing ROB No. 229, a composite girder bridge at chainage KM 105.06, located between Nuagaon and Daspalla. The company is also providing construction vehicles, site infrastructure, and auxiliary services required to support the project’s execution.Shri Rajesh Kumar Das, Deputy Chief Engineer of ECoR, stated that once completed, the viaduct will be second in length only to the Bogibeel Bridge over the Brahmaputra in Assam.The alignment of the railway had to be altered due to its intersection with the upcoming Brutang irrigation project in Nayagarh district. A substantial part of the railway route was originally set to pass through the planned reservoir. Following consultations with the Odisha Water Resources Department, the alignment was modified to include the 4.77-kilometre viaduct, thereby avoiding disruption to the reservoir infrastructure.In parallel, another viaduct measuring 1,257.6 metres is under construction in Boudh district as part of the same new line project. Shri Das noted that the 75-kilometre segment between Daspalla and Purunakatak will offer passengers a scenic route, with the viaduct and seven tunnels passing through dense forest regions in Nayagarh and Boudh.
Next Story
Greater Noida Film City to Begin with Rs 1.5 Billion First Phase
Greater Noida is set to host one of India’s most ambitious entertainment infrastructure projects with the upcoming International Film City in Sector 21, along the Yamuna Expressway. The Uttar Pradesh government, led by Chief Minister Yogi Adityanath, is expected to lay the foundation stone in late June, either in person or via video conference. While June 16 has been speculated, the final date is yet to be officially confirmed.The project is being developed by Bayview Bhutani Film City Pvt Ltd—a joint venture between filmmaker Boney Kapoor and the Bhutani Group—in collaboration with the ..
Next Story
CCL to Add 2 New Mines, Boosting Output by 12 MT
Coal India subsidiary Central Coalfields Ltd (CCL) is set to commission two new coal mines in the 2025�26 financial year, aiming to enhance its annual production capacity by 10 to 12 million tonnes. The initiative is part of the company’s broader plan to exceed 110 million tonnes of coal production this fiscal and reach 150 million tonnes by 2030.“We have planned to open two new mines this year,� said Nilendu Kumar Singh, Chairman and Managing Director of CCL.Production at the Kotre Basantpur block, a coking coal mine with a peak rated capacity of 5 million tonnes per annum, is expecte..
Next Story
India Cements Sells ICML Stake for Rs 980 Million
India Cements has announced the sale of its entire equity holding in Industrial Chemicals and Monomers Ltd (ICML) to Mirai Sensing Private Ltd for a consideration of Rs 980 million. The transaction was disclosed through a regulatory filing with the Bombay Stock Exchange.Following the completion of this sale, ICML will cease to be a subsidiary of India Cements, the filing confirmed.ICML, registered in Tirunelveli, Tamil Nadu, had earlier suspended operations. According to the company’s annual report for 2024, the business had become unviable due to reasons previously disclosed. The report fur..