Smart City work near Caculo Mall may miss May 31 target
SMART CITIES

Smart City work near Caculo Mall may miss May 31 target

The Imagine Panaji Smart City Development (IPSCDL) seems to be considering skipping the smart road work from Caculo Mall to the Tonca sewerage treatment plant (STP) due to practical challenges, despite the May 31 deadline for completing all ongoing smart city work in Panaji.

According to IPSCDL, the cumulative target for completing all road works and making the road functional is May 31. However, they mentioned that this particular stretch might take a "little longer" to finish. IPSCDL stated that major challenges have been encountered in drilling due to the depth of sewerage works along the stretch, which is nearly 8 meters below road level and below the bed of the St Inez creek.

Out of the total 430 metres, the main trunk pipeline of 300 meters has been laid, and work on the remaining 130 meters, which passes under the St Inez creek and connects to the Tonca STP, is currently in progress. IPSCDL added that along this stretch, one out of nine manholes has been completed, and another one is in progress.

IPSCDL, led by its CEO Sanjit Rodrigues, is monitoring the ongoing sewerage work on the stretch on an hourly basis to meet the May 31 deadline. Regarding the stretch from the Four Pillar junction to the Old Patto bridge, the contractor appointed by IPSCDL has completed all major sewerage works, including laying a total pipeline of 1,400 meters, constructing 40 manholes, and installing 80 house connection chambers. Only one inter-connection is pending, which is expected to be completed in a couple of days. Currently, road restoration work is underway.

IPSCDL mentioned that road construction on this stretch for the smart road project can only commence after the Public Works Department (PWD) finishes installing new pumping lines to connect pump houses located at Mala, near Bhandari hospital, and near the income tax office.

The Imagine Panaji Smart City Development (IPSCDL) seems to be considering skipping the smart road work from Caculo Mall to the Tonca sewerage treatment plant (STP) due to practical challenges, despite the May 31 deadline for completing all ongoing smart city work in Panaji. According to IPSCDL, the cumulative target for completing all road works and making the road functional is May 31. However, they mentioned that this particular stretch might take a little longer to finish. IPSCDL stated that major challenges have been encountered in drilling due to the depth of sewerage works along the stretch, which is nearly 8 meters below road level and below the bed of the St Inez creek. Out of the total 430 metres, the main trunk pipeline of 300 meters has been laid, and work on the remaining 130 meters, which passes under the St Inez creek and connects to the Tonca STP, is currently in progress. IPSCDL added that along this stretch, one out of nine manholes has been completed, and another one is in progress. IPSCDL, led by its CEO Sanjit Rodrigues, is monitoring the ongoing sewerage work on the stretch on an hourly basis to meet the May 31 deadline. Regarding the stretch from the Four Pillar junction to the Old Patto bridge, the contractor appointed by IPSCDL has completed all major sewerage works, including laying a total pipeline of 1,400 meters, constructing 40 manholes, and installing 80 house connection chambers. Only one inter-connection is pending, which is expected to be completed in a couple of days. Currently, road restoration work is underway. IPSCDL mentioned that road construction on this stretch for the smart road project can only commence after the Public Works Department (PWD) finishes installing new pumping lines to connect pump houses located at Mala, near Bhandari hospital, and near the income tax office.

Next Story
Real Estate

Swamiraj Rebrands as House of Swamiraj, Announces Rs 210 Cr Project

In a strategic shift marking its evolution from a reputed builder to a lifestyle-focused brand, Swamiraj Constructions has rebranded as House of Swamiraj. With a two-decade legacy and over 1,700 homes delivered across the Mumbai Metropolitan Region (MMR), the company is embracing a new phase centred on community-driven, wellness-oriented living. The rebranding was unveiled via a digital campaign titled #BeyondDimensions, executed in three phases鈥攖easer, engagement, and launch. The campaign spotlighted the brand鈥檚 renewed commitment to designing homes that go beyond function to foster ..

Next Story
Resources

Morpho Dimensions Set to Cross Rs 1 billion Revenue in FY 25鈥�26

Morpho Dimensions, a venture of acclaimed architecture and design firm Morphogenesis, is transforming India鈥檚 office interiors landscape with a technology-first, design-led approach. With a secured orderbook of Rs 700 million and additional projects in the pipeline, the firm is confidently on track to cross Rs 1 billion in revenue in FY 2025鈥�26.聽By combining Artificial Intelligence (AI), Building Information Modelling (BIM), and Virtual Reality (VR), Morpho Dimensions enables clients to visualise and step into immersive, ready-to-operate workspaces within 90 days鈥攗shering in a new bench..

Next Story
Real Estate

TOTO鈥檚 NEOREST Surpasses 4 Million Global Shipments

TOTO has announced that its flagship smart toilet, NEOREST, has surpassed 4 million global shipments as of March 2025, marking a major milestone in the evolution of luxury sanitation and setting a new global benchmark in design-led hygiene innovation. Launched in 1993 with the aim to redefine conventional toilets, NEOREST has consistently merged cutting-edge technology with minimalist design. Over three decades, it has become a category-defining product, earning global acclaim with prestigious honours including the iF Design Award, Red Dot, and Green Good Design Awards. The integrate..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement