TN power projects seeks govt's help to develop coal block in Angul
25 Jan 2022
2 Min Read
CW Team
With three new thermal power projects getting ready to go live in Tamil Nadu, the Tamil Nadu Generation and Distribution Corporation (TANGEDCO) has sought support from the central government and the Odisha government for developing a coal block in Odisha鈥檚 Angul.
An official told the media that the three new thermal power stations with 3,440 MW capacity would require 30,000-40,000 tonnes of additional coal daily. The Centre had allotted the Chandrabilla coal block to the State power utility in 2016. The period of coal excavation from the block was between 2016-2021.
The development of the coal block was delayed due to the lack of clearance for exploration in the forest area by the Ministry of Environment, Forest and Climate Change (MoEFCC).
An official said that if the Centre does not approve the Chandrabilla coal block, TANGEDCO has to purchase fuel from private entities.
The construction work of the upcoming coal-fired North Chennai stage III is already complete, and the other terminal projects, Ennore Special Economic Zone (SEZ) and Udangudi, are about 95% completed.
The Tamil Nadu government plans to commence the North Chennai stage-III project before May 2022 and other projects by the end of 2022. An official said that TANGEDCO had invited bids of Rs 21,000 crore to hand over the Chandrabilla coal mine project.
However, no bidder came up, and the project was further delayed due to the Covid-19 pandemic.
The state power utility urged the Odisha government to help seek clearance from the Forest Department. Previously, TN Electricity Minister V Senthil Balaji and the Chairman of TANGEDCO, Rajesh Lakhani, urged the Ministry of Power, R K Singh, to initiate the step, hoping to commence the Chandrabilla coal block as early as possible.
The thermal power stations of 4,320 MW in North Chennai, Mettur and Tuticorin require 62,000 tonnes of coal daily. India had witnessed a coal shortage, and several thermal power stations were on the verge of shutting down.
Also read: Govt to ask 79 coal-based power plants to set up anti-emission gear
Also read: Coal India transports 91% coal stocks to thermal power plants
With three new thermal power projects getting ready to go live in Tamil Nadu, the Tamil Nadu Generation and Distribution Corporation (TANGEDCO) has sought support from the central government and the Odisha government for developing a coal block in Odisha鈥檚 Angul.
An official told the media that the three new thermal power stations with 3,440 MW capacity would require 30,000-40,000 tonnes of additional coal daily. The Centre had allotted the Chandrabilla coal block to the State power utility in 2016. The period of coal excavation from the block was between 2016-2021.
The development of the coal block was delayed due to the lack of clearance for exploration in the forest area by the Ministry of Environment, Forest and Climate Change (MoEFCC).
An official said that if the Centre does not approve the Chandrabilla coal block, TANGEDCO has to purchase fuel from private entities.
The construction work of the upcoming coal-fired North Chennai stage III is already complete, and the other terminal projects, Ennore Special Economic Zone (SEZ) and Udangudi, are about 95% completed.
The Tamil Nadu government plans to commence the North Chennai stage-III project before May 2022 and other projects by the end of 2022. An official said that TANGEDCO had invited bids of Rs 21,000 crore to hand over the Chandrabilla coal mine project.
However, no bidder came up, and the project was further delayed due to the Covid-19 pandemic.
The state power utility urged the Odisha government to help seek clearance from the Forest Department. Previously, TN Electricity Minister V Senthil Balaji and the Chairman of TANGEDCO, Rajesh Lakhani, urged the Ministry of Power, R K Singh, to initiate the step, hoping to commence the Chandrabilla coal block as early as possible.
The thermal power stations of 4,320 MW in North Chennai, Mettur and Tuticorin require 62,000 tonnes of coal daily. India had witnessed a coal shortage, and several thermal power stations were on the verge of shutting down.
Image Source
Also read: Govt to ask 79 coal-based power plants to set up anti-emission gear
Also read: Coal India transports 91% coal stocks to thermal power plants
Next Story
Swamiraj Rebrands as House of Swamiraj, Announces Rs 210 Cr Project
In a strategic shift marking its evolution from a reputed builder to a lifestyle-focused brand, Swamiraj Constructions has rebranded as House of Swamiraj. With a two-decade legacy and over 1,700 homes delivered across the Mumbai Metropolitan Region (MMR), the company is embracing a new phase centred on community-driven, wellness-oriented living. The rebranding was unveiled via a digital campaign titled #BeyondDimensions, executed in three phases鈥攖easer, engagement, and launch. The campaign spotlighted the brand鈥檚 renewed commitment to designing homes that go beyond function to foster ..
Next Story
Morpho Dimensions Set to Cross Rs 1 billion Revenue in FY 25鈥�26
Morpho Dimensions, a venture of acclaimed architecture and design firm Morphogenesis, is transforming India鈥檚 office interiors landscape with a technology-first, design-led approach. With a secured orderbook of Rs 700 million and additional projects in the pipeline, the firm is confidently on track to cross Rs 1 billion in revenue in FY 2025鈥�26.聽By combining Artificial Intelligence (AI), Building Information Modelling (BIM), and Virtual Reality (VR), Morpho Dimensions enables clients to visualise and step into immersive, ready-to-operate workspaces within 90 days鈥攗shering in a new bench..
Next Story
TOTO鈥檚 NEOREST Surpasses 4 Million Global Shipments
TOTO has announced that its flagship smart toilet, NEOREST, has surpassed 4 million global shipments as of March 2025, marking a major milestone in the evolution of luxury sanitation and setting a new global benchmark in design-led hygiene innovation. Launched in 1993 with the aim to redefine conventional toilets, NEOREST has consistently merged cutting-edge technology with minimalist design. Over three decades, it has become a category-defining product, earning global acclaim with prestigious honours including the iF Design Award, Red Dot, and Green Good Design Awards. The integrate..