Chennai Airport Sees Early Phase 2 Completion
26 Feb 2025
2 Min Read
CW Team
The Phase 2 expansion of Chennai International Airport is progressing at an accelerated pace, with efforts underway to prevent further delays. As per the revised schedule, the second portion of the new integrated terminal is expected to be ready by early 2026, with operations set to commence by March.
Revised Timelines and Project Scope
Initially, in 2023, then Civil Aviation Minister VK Singh had projected July 2025 as the completion date for the airport’s renovation. However, the Airports Authority of India (AAI) later revised the timeline to December 2025, before setting a final completion target of March 2026.
Launched in 2018 with an estimated investment of Rs 24.67 billion, the expansion aims to boost annual passenger capacity from 2.3 crore to 3.5 crore. The works span across a 2.36 lakh sq m area, making it one of the largest airport expansion projects in India.
The expansion has been structured in two phases, “The current peak-hour footfall in the existing terminal is around 12,000 passengers. With the new terminal’s expanded space and upgraded facilities, passenger movement will be smoother and waiting times significantly reduced,� said an airport official.
Boosting Capacity and Future Expansion Plans
Currently, Chennai Airport operates with three terminals—T1, T2, and T4. The addition of T3 will elevate its annual passenger-handling capacity to 3.5 crore, with flight operations exceeding 500 per day.
Exclusive 5th Terminal Planned for Cargo Operations
Airport authorities have also revealed plans to develop a 5th terminal dedicated solely to cargo flights once T3 is operational. The required land is already available, and if all goes as planned, construction on T5 will commence soon.
This ambitious expansion underscores Chennai Airport’s transformation into a world-class aviation hub, positioning it to handle rising passenger demand and bolster cargo operations in the years to come.
The Phase 2 expansion of Chennai International Airport is progressing at an accelerated pace, with efforts underway to prevent further delays. As per the revised schedule, the second portion of the new integrated terminal is expected to be ready by early 2026, with operations set to commence by March.
Revised Timelines and Project Scope
Initially, in 2023, then Civil Aviation Minister VK Singh had projected July 2025 as the completion date for the airport’s renovation. However, the Airports Authority of India (AAI) later revised the timeline to December 2025, before setting a final completion target of March 2026.
Launched in 2018 with an estimated investment of Rs 24.67 billion, the expansion aims to boost annual passenger capacity from 2.3 crore to 3.5 crore. The works span across a 2.36 lakh sq m area, making it one of the largest airport expansion projects in India.
The expansion has been structured in two phases, “The current peak-hour footfall in the existing terminal is around 12,000 passengers. With the new terminal’s expanded space and upgraded facilities, passenger movement will be smoother and waiting times significantly reduced,� said an airport official.
Boosting Capacity and Future Expansion Plans
Currently, Chennai Airport operates with three terminals—T1, T2, and T4. The addition of T3 will elevate its annual passenger-handling capacity to 3.5 crore, with flight operations exceeding 500 per day.
Exclusive 5th Terminal Planned for Cargo Operations
Airport authorities have also revealed plans to develop a 5th terminal dedicated solely to cargo flights once T3 is operational. The required land is already available, and if all goes as planned, construction on T5 will commence soon.
This ambitious expansion underscores Chennai Airport’s transformation into a world-class aviation hub, positioning it to handle rising passenger demand and bolster cargo operations in the years to come.
Next Story
MoHUA Plans New Role for Smart City SPVs
In a significant policy move, the Ministry of Housing and Urban Affairs (MoHUA) has issued an advisory encouraging the continued use and repurposing of Special Purpose Vehicles (SPVs) formed under the Smart Cities Mission (SCM). This marks a step toward sustaining urban transformation by leveraging institutional capabilities and infrastructure developed over the past decade.Initiated in 2015, the Smart Cities Mission introduced a new era of urban planning in India, with each of the 100 selected cities forming SPVs under the Companies Act, 2013. These entities, jointly owned by state government..
Next Story
ADB Approves $110 Million Loan to Boost Skills in Gujarat
The Asian Development Bank (ADB) has approved a USD 109.97 million (Rs 9.27 billion) results-based loan to support Gujarat’s efforts to become a global industrial hub by developing a future-ready, skilled workforce.The funding will back the Gujarat skills development programme, led by the Department of Labour, Skill Development and Employment in collaboration with Kaushalya: The Skill University (KSU). The initiative aims to equip the workforce with advanced, industry-aligned skills to meet rising employment demand in high-growth sectors.According to ADB, the programme seeks to strengthen in..
Next Story
SDAL Tests Rudrastra UAV and Bhargavastra Defence System
Solar Defence and Aerospace Limited (SDAL) has successfully completed a key flight test of its indigenous Hybrid VTOL UAV Rudrastra at the Pokharan Firing Range, aligning with Indian Army performance benchmarks for mission adaptability, high endurance, precision engagement, and vertical take-off and landing (VTOL) capability.The trial marks a notable achievement in India’s Aatmanirbhar Bharat initiative, underscoring advancements in home-grown military technology. The Rudrastra UAV demonstrated a mission radius exceeding 50 km with uninterrupted video relay, a total operational range of over..