Telangana cancels Keshavapuram contract
11 Nov 2024
2 Min Read
CW Team
The Telangana government has scrapped the Keshavapuram project, initially proposed under the previous BRS regime, which was designed to meet Hyderabad's drinking water needs through the Godavari Phase-2 project. Instead, the government has decided to source 15 tmcft of water from Mallannasagar.
The original plan aimed to lift 10 tmcft of water from Kondapochamma Sagar and fill the Keshavapuram reservoir, from where the water would be pumped to Hyderabad. The cancellation was confirmed by the Municipal Administration department on Tuesday, with the decision made public on Wednesday.
Government sources indicated that the Mallannasagar option would save approximately Rs 2,000 crore. Of the 15 tmcft to be lifted, 10 tmcft will be used for Hyderabad's drinking water, while the remaining 5 tmcft will be used to replenish Osmansagar and Himayathsagar.
The Cabinet approved this shift, and tenders are expected to be invited for a new project titled "Godavari Drinking Water Supply Phase-2 and Rejuvenation of Osmansagar and Himayathsagar for Musi River Cleanup." The new plan includes laying a pipeline to transport 15 tmcft of water from Mallannasagar to the Ghanpur pumphouse for distribution to Hyderabad and the reservoirs.
Sources highlighted that Mallannasagar has a capacity of 50 tmcft, whereas Kondapochamma Sagar can only hold 16 tmcft. This change reduces the need for multiple pumping stations, cutting operational costs and electricity usage. The cost of supplying water from the Godavari and Krishna rivers is expected to decrease from Rs 48 per KLD to Rs 4 per KLD once the project is completed.
The Keshavapuram project contract had been awarded to Megha Engineering and Infrastructure Limited (MEIL), but work did not start. MEIL requested a revision of the cost estimates based on the 2024 rates, which was rejected by the state government.
The Telangana government has scrapped the Keshavapuram project, initially proposed under the previous BRS regime, which was designed to meet Hyderabad's drinking water needs through the Godavari Phase-2 project. Instead, the government has decided to source 15 tmcft of water from Mallannasagar.
The original plan aimed to lift 10 tmcft of water from Kondapochamma Sagar and fill the Keshavapuram reservoir, from where the water would be pumped to Hyderabad. The cancellation was confirmed by the Municipal Administration department on Tuesday, with the decision made public on Wednesday.
Government sources indicated that the Mallannasagar option would save approximately Rs 2,000 crore. Of the 15 tmcft to be lifted, 10 tmcft will be used for Hyderabad's drinking water, while the remaining 5 tmcft will be used to replenish Osmansagar and Himayathsagar.
The Cabinet approved this shift, and tenders are expected to be invited for a new project titled Godavari Drinking Water Supply Phase-2 and Rejuvenation of Osmansagar and Himayathsagar for Musi River Cleanup. The new plan includes laying a pipeline to transport 15 tmcft of water from Mallannasagar to the Ghanpur pumphouse for distribution to Hyderabad and the reservoirs.
Sources highlighted that Mallannasagar has a capacity of 50 tmcft, whereas Kondapochamma Sagar can only hold 16 tmcft. This change reduces the need for multiple pumping stations, cutting operational costs and electricity usage. The cost of supplying water from the Godavari and Krishna rivers is expected to decrease from Rs 48 per KLD to Rs 4 per KLD once the project is completed.
The Keshavapuram project contract had been awarded to Megha Engineering and Infrastructure Limited (MEIL), but work did not start. MEIL requested a revision of the cost estimates based on the 2024 rates, which was rejected by the state government.
Next Story
MoHUA Plans New Role for Smart City SPVs
In a significant policy move, the Ministry of Housing and Urban Affairs (MoHUA) has issued an advisory encouraging the continued use and repurposing of Special Purpose Vehicles (SPVs) formed under the Smart Cities Mission (SCM). This marks a step toward sustaining urban transformation by leveraging institutional capabilities and infrastructure developed over the past decade.Initiated in 2015, the Smart Cities Mission introduced a new era of urban planning in India, with each of the 100 selected cities forming SPVs under the Companies Act, 2013. These entities, jointly owned by state government..
Next Story
ADB Approves $110 Million Loan to Boost Skills in Gujarat
The Asian Development Bank (ADB) has approved a USD 109.97 million (Rs 9.27 billion) results-based loan to support Gujarat’s efforts to become a global industrial hub by developing a future-ready, skilled workforce.The funding will back the Gujarat skills development programme, led by the Department of Labour, Skill Development and Employment in collaboration with Kaushalya: The Skill University (KSU). The initiative aims to equip the workforce with advanced, industry-aligned skills to meet rising employment demand in high-growth sectors.According to ADB, the programme seeks to strengthen in..
Next Story
SDAL Tests Rudrastra UAV and Bhargavastra Defence System
Solar Defence and Aerospace Limited (SDAL) has successfully completed a key flight test of its indigenous Hybrid VTOL UAV Rudrastra at the Pokharan Firing Range, aligning with Indian Army performance benchmarks for mission adaptability, high endurance, precision engagement, and vertical take-off and landing (VTOL) capability.The trial marks a notable achievement in India’s Aatmanirbhar Bharat initiative, underscoring advancements in home-grown military technology. The Rudrastra UAV demonstrated a mission radius exceeding 50 km with uninterrupted video relay, a total operational range of over..