 Mumbai Metro lines 2A and 7 likely to be partially operational by Feb
RAILWAYS & METRO RAIL

Mumbai Metro lines 2A and 7 likely to be partially operational by Feb

Mumbai Metro lines 2A and 7 are likely to become partially operational before February 2022, and the entire corridor is likely to start by July 2022.

Metro 7 line will operate from Dahisar to Western Express Highway, Andheri, and 2A from Dahisar to D N Nagar. A senior Mumbai Metropolitan Region Development Authority (MMRDA) official told the media that about 95% of the work on Phase I is done, and they are confident of beginning the lines in two to three months. The first phase covering 20 km is between Dahanukarwadi to Aarey (18 stations). Both these Metro lines are likely to lessen vehicular traffic by 25%.

In September, MMRDA had served show-cause notices to four contractors鈥擩 Kumar Infraprojects, NCC, Godrej and Capacite Infraprojects鈥攆or the delay in developing Metro station works. The total penalty amounting to over Rs 2 crore will be collected if they fail to achieve the work within the given timeframe.

The official said that the showcauses notices have served as a deterrent, and contractors can match the timeline since they have managed to mobilise manpower and machinery to achieve the balance station works. They have not inflicted any penalty yet, but the show cause notices have not been revoked.

MMRDA had expected to begin these lines by October 2019. Later, this deadline was updated to December last year. The pandemic in early 2020 resulted in a lockdown and fleeing of labourers to their native place due to which work had come to a pause. The commercial operations were later aimed to start from October 2021 between Kamraj Nagar and Aarey via Dahisar on both lines.

The commissioning timeline for the complete stretch of lines 2A and 7 was previously set on January 1, 2022. MMRDA aims to operate services with 11 rakes at a frequency of 15 to 20 minutes initially. As and when rakes get added, the frequency will dip to 5 minutes per train. Both these Metro lines were approved by the Devendra Fadnavis-led government on October 6, 2015.

Mumbai Metro lines 2A and 7 are likely to become partially operational before February 2022, and the entire corridor is likely to start by July 2022. Metro 7 line will operate from Dahisar to Western Express Highway, Andheri, and 2A from Dahisar to D N Nagar. A senior Mumbai Metropolitan Region Development Authority (MMRDA) official told the media that about 95% of the work on Phase I is done, and they are confident of beginning the lines in two to three months. The first phase covering 20 km is between Dahanukarwadi to Aarey (18 stations). Both these Metro lines are likely to lessen vehicular traffic by 25%. In September, MMRDA had served show-cause notices to four contractors鈥擩 Kumar Infraprojects, NCC, Godrej and Capacite Infraprojects鈥攆or the delay in developing Metro station works. The total penalty amounting to over Rs 2 crore will be collected if they fail to achieve the work within the given timeframe. The official said that the showcauses notices have served as a deterrent, and contractors can match the timeline since they have managed to mobilise manpower and machinery to achieve the balance station works. They have not inflicted any penalty yet, but the show cause notices have not been revoked. MMRDA had expected to begin these lines by October 2019. Later, this deadline was updated to December last year. The pandemic in early 2020 resulted in a lockdown and fleeing of labourers to their native place due to which work had come to a pause. The commercial operations were later aimed to start from October 2021 between Kamraj Nagar and Aarey via Dahisar on both lines. The commissioning timeline for the complete stretch of lines 2A and 7 was previously set on January 1, 2022. MMRDA aims to operate services with 11 rakes at a frequency of 15 to 20 minutes initially. As and when rakes get added, the frequency will dip to 5 minutes per train. Both these Metro lines were approved by the Devendra Fadnavis-led government on October 6, 2015. Image Source

Next Story
Infrastructure Transport

NHAI to List Highways With Long-Term Monetisation Potential

The National Highways Authority of India (NHAI) is set to create a dedicated register of highway assets with long-term monetisation potential, complementing its existing annual list of roads earmarked for commercialisation through toll-operate-transfer (TOT) and infrastructure investment trust (InvIT) models.The initiative aims to maximise asset value and offer investors greater visibility into potential future opportunities. According to officials, this register will include technical and financial data to assess revenue viability, allowing investors to formulate strategic plans for engagemen..

Next Story
Infrastructure Transport

AVP Infracon Wins Rs 160 Million Bridge Project in Tamil Nadu

AVP Infracon Limited, a leading player in India鈥檚 infrastructure sector, has secured a Letter of Acceptance (LoA) from the Superintending Engineer, Highways NABARD & Rural Roads Circle, Salem, for the construction of a Road Over Bridge (ROB) at Km 0/6 of Thaneerpandal Road in Tamil Nadu. The ROB will replace Level Crossing No. 6 located between Singanallur and Peelamedu railway stations within the Coimbatore region.The government-awarded contract is valued at approximately Rs 160 million and is to be completed within 18 months from the project's commencement.The bridge is expected to sig..

Next Story
Infrastructure Transport

NHAI To Study Underpass Plan at Khandsa Junction

The National Highways Authority of India (NHAI) will undertake a feasibility study for a proposed underpass at the Khandsa intersection in Gurugram to help decongest traffic between Hero Honda Chowk and Umang Bhardwaj Chowk. The underpass is intended to improve vehicle movement from Sector 10 Road to Mohammadpur Jharsa Road, with the study expected to conclude by next month.The proposal was discussed in a recent review meeting chaired by Union Minister and Gurugram MP Rao Inderjit Singh, who supported the plan and highlighted its potential to streamline traffic at the busy junction.A senior NH..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement