BKC-Acharya Atre Metro Among 3 Projects Halted in Maharashtra
07 May 2025
2 Min Read
CW Team
Several major infrastructure and transport projects in Mumbai, which were initially scheduled to be inaugurated by Prime Minister Narendra Modi on May 1, have been postponed due to heightened security concerns. The affected projects include the partial opening of Mumbai Metro Line 3 from Bandra Kurla Complex (BKC) to Acharya Atre Chowk, the completion of the Igatpuri-to-Thane stretch of the Samruddhi Mahamarg Expressway, and the opening of the Mumbai-bound lane of the new Thane Creek Bridge. Another significant project impacted is the handover of newly redeveloped homes at BDD Chawl in Worli. A report from FPJ stated that the decision to postpone the projects was made following a recent terrorist attack in Pahalgam, Jammu and Kashmir, on April 22.
The delay will affect a wide range of people. Daily commuters in Mumbai, particularly those travelling through congested areas like Worli, Mahalaxmi, and BKC, will have to continue relying on overcrowded local trains and slow road traffic due to the metro line remaining shut. Office-goers and business employees in BKC will miss out on faster transport options.
The postponement of the Igatpuri-to-Thane expressway segment will lead to longer travel times for truck drivers, transport companies, and anyone travelling between Nagpur and Mumbai. Residents in Nashik, Igatpuri, and Thane will also not benefit from the expected improvements in connectivity and local development.
Similarly, the delay of the new Mumbai-bound lane of the Thane Creek Bridge will prevent relief for thousands of people commuting into Mumbai from Thane and Navi Mumbai, meaning traffic jams and travel delays will persist, particularly during peak hours.
Residents of BDD Chawl in Worli, who were eager to move into their newly constructed homes, will have to wait longer for the official handover.
Before the attack in Pahalgam, a large public event was being planned at BKC to mark the openings. However, now, smaller events or a joint ceremony led by the Maharashtra Chief Minister and his deputies are under consideration. Final decisions will be made based on security updates and the revised schedule of the Prime Minister.
News source: Times Now News
Several major infrastructure and transport projects in Mumbai, which were initially scheduled to be inaugurated by Prime Minister Narendra Modi on May 1, have been postponed due to heightened security concerns. The affected projects include the partial opening of Mumbai Metro Line 3 from Bandra Kurla Complex (BKC) to Acharya Atre Chowk, the completion of the Igatpuri-to-Thane stretch of the Samruddhi Mahamarg Expressway, and the opening of the Mumbai-bound lane of the new Thane Creek Bridge. Another significant project impacted is the handover of newly redeveloped homes at BDD Chawl in Worli. A report from FPJ stated that the decision to postpone the projects was made following a recent terrorist attack in Pahalgam, Jammu and Kashmir, on April 22.
The delay will affect a wide range of people. Daily commuters in Mumbai, particularly those travelling through congested areas like Worli, Mahalaxmi, and BKC, will have to continue relying on overcrowded local trains and slow road traffic due to the metro line remaining shut. Office-goers and business employees in BKC will miss out on faster transport options.
The postponement of the Igatpuri-to-Thane expressway segment will lead to longer travel times for truck drivers, transport companies, and anyone travelling between Nagpur and Mumbai. Residents in Nashik, Igatpuri, and Thane will also not benefit from the expected improvements in connectivity and local development.
Similarly, the delay of the new Mumbai-bound lane of the Thane Creek Bridge will prevent relief for thousands of people commuting into Mumbai from Thane and Navi Mumbai, meaning traffic jams and travel delays will persist, particularly during peak hours.
Residents of BDD Chawl in Worli, who were eager to move into their newly constructed homes, will have to wait longer for the official handover.
Before the attack in Pahalgam, a large public event was being planned at BKC to mark the openings. However, now, smaller events or a joint ceremony led by the Maharashtra Chief Minister and his deputies are under consideration. Final decisions will be made based on security updates and the revised schedule of the Prime Minister.
News source: Times Now News
Next Story
MoHUA Plans New Role for Smart City SPVs
In a significant policy move, the Ministry of Housing and Urban Affairs (MoHUA) has issued an advisory encouraging the continued use and repurposing of Special Purpose Vehicles (SPVs) formed under the Smart Cities Mission (SCM). This marks a step toward sustaining urban transformation by leveraging institutional capabilities and infrastructure developed over the past decade.Initiated in 2015, the Smart Cities Mission introduced a new era of urban planning in India, with each of the 100 selected cities forming SPVs under the Companies Act, 2013. These entities, jointly owned by state government..
Next Story
ADB Approves $110 Million Loan to Boost Skills in Gujarat
The Asian Development Bank (ADB) has approved a USD 109.97 million (Rs 9.27 billion) results-based loan to support Gujarat鈥檚 efforts to become a global industrial hub by developing a future-ready, skilled workforce.The funding will back the Gujarat skills development programme, led by the Department of Labour, Skill Development and Employment in collaboration with Kaushalya: The Skill University (KSU). The initiative aims to equip the workforce with advanced, industry-aligned skills to meet rising employment demand in high-growth sectors.According to ADB, the programme seeks to strengthen in..
Next Story
SDAL Tests Rudrastra UAV and Bhargavastra Defence System
Solar Defence and Aerospace Limited (SDAL) has successfully completed a key flight test of its indigenous Hybrid VTOL UAV Rudrastra at the Pokharan Firing Range, aligning with Indian Army performance benchmarks for mission adaptability, high endurance, precision engagement, and vertical take-off and landing (VTOL) capability.The trial marks a notable achievement in India鈥檚 Aatmanirbhar Bharat initiative, underscoring advancements in home-grown military technology. The Rudrastra UAV demonstrated a mission radius exceeding 50 km with uninterrupted video relay, a total operational range of over..