DFCCIL proposes de-risking private participation in developing DFC
24 Sep 2021
2 Min Read
CW Team
The Dedicated Freight Corridor Corporation of India (DFCCIL) has proposed derisking the private party developing the Sonnagar (New Chirailapauthu) to Andal section of the Eastern Dedicated Freight Corridor (DFC).
This section of the DFC will be developed by DFCCIL using a Design, Finance, Build, Operate, and Maintain & Transfer (DFBOT) approach with Public Private Partnership (PPP).
Private players expressed scepticism of projected traffic at the proposed section of the freight corridor over the 30-year contract period, according to the Managing Director at DFCCIL, R K Jain.
To address the issue, Jain said that the Indian Railways and DFCCIL will take over the traffic and tariff risk, which will reduce the risk on the concessionaire.
According to him, the concessionaire will be in charge of the project's design, construction, finance, operations, and maintenance.
The major powerhouses, industrial corridors, and Multi-Modal Logistics Parks (MMLPs) in Delhi, Haryana, Punjab, and Uttar Pradesh are expected to be served by this section. Steel traffic on the route will grow due to rising trends in finished steel consumption and production.
DFCCIL also plans to develop MMLPs, sidings, and feeder routes for last-mile connectivity along the section alignment to attract more traffic and achieve a targeted rail freight share.
The DFCCIL has been consulting with private stakeholders on how to proceed with the project.
Potential bidders are concerned that lower coal demand in the future, as more renewable energy projects emerge, will jeopardise the viability of freight operations on this route.
Another concern is that, because train operations are ultimately under the control of the railways, there may be fewer trains on the freight corridor to save money. The third source of concern was a potential alternative route, such as a parallel road route, which could eat into rail freight traffic.
According to Jain, it is proposed that the concessionaire be paid a fixed amount for operation and maintenance (O&M) fees, regardless of the amount of traffic on the route.
The bidders will compete based on the amount of money they want in exchange for their services.
He said that the concessionaire will be responsible for ensuring a daily uptime of 20 hours. He added that they would be free to hire people on their own terms.
Also read: DFCCIL floats tender for Ro-Ro on western corridor
The Dedicated Freight Corridor Corporation of India (DFCCIL) has proposed derisking the private party developing the Sonnagar (New Chirailapauthu) to Andal section of the Eastern Dedicated Freight Corridor (DFC).
This section of the DFC will be developed by DFCCIL using a Design, Finance, Build, Operate, and Maintain & Transfer (DFBOT) approach with Public Private Partnership (PPP).
Private players expressed scepticism of projected traffic at the proposed section of the freight corridor over the 30-year contract period, according to the Managing Director at DFCCIL, R K Jain.
To address the issue, Jain said that the Indian Railways and DFCCIL will take over the traffic and tariff risk, which will reduce the risk on the concessionaire.
According to him, the concessionaire will be in charge of the project's design, construction, finance, operations, and maintenance.
The major powerhouses, industrial corridors, and Multi-Modal Logistics Parks (MMLPs) in Delhi, Haryana, Punjab, and Uttar Pradesh are expected to be served by this section. Steel traffic on the route will grow due to rising trends in finished steel consumption and production.
DFCCIL also plans to develop MMLPs, sidings, and feeder routes for last-mile connectivity along the section alignment to attract more traffic and achieve a targeted rail freight share.
The DFCCIL has been consulting with private stakeholders on how to proceed with the project.
Potential bidders are concerned that lower coal demand in the future, as more renewable energy projects emerge, will jeopardise the viability of freight operations on this route.
Another concern is that, because train operations are ultimately under the control of the railways, there may be fewer trains on the freight corridor to save money. The third source of concern was a potential alternative route, such as a parallel road route, which could eat into rail freight traffic.
According to Jain, it is proposed that the concessionaire be paid a fixed amount for operation and maintenance (O&M) fees, regardless of the amount of traffic on the route.
The bidders will compete based on the amount of money they want in exchange for their services.
He said that the concessionaire will be responsible for ensuring a daily uptime of 20 hours. He added that they would be free to hire people on their own terms.
Image SourceAlso read: DFCCIL floats tender for Ro-Ro on western corridor
Next Story
NHAI To Study Underpass Plan at Khandsa Junction
The National Highways Authority of India (NHAI) will undertake a feasibility study for a proposed underpass at the Khandsa intersection in Gurugram to help decongest traffic between Hero Honda Chowk and Umang Bhardwaj Chowk. The underpass is intended to improve vehicle movement from Sector 10 Road to Mohammadpur Jharsa Road, with the study expected to conclude by next month.The proposal was discussed in a recent review meeting chaired by Union Minister and Gurugram MP Rao Inderjit Singh, who supported the plan and highlighted its potential to streamline traffic at the busy junction.A senior NH..
Next Story
MP Approves Rs 2.6 Trillion Rural Road Plan for Tribals
The Madhya Pradesh government has approved the Mukhyamantri Majra-Tola Sadak Yojana, a major infrastructure initiative aimed at enhancing road connectivity for tribal communities in remote rural areas. The Cabinet, chaired by Chief Minister Mohan Yadav, has allocated Rs 2.6 trillion (Rs 2,600 billion) for the project鈥檚 implementation.The scheme targets the construction of 30,900 km of rural roads across two phases: the first phase will run from 2025鈥�26 to 2029鈥�30, followed by a second phase from 2030鈥�31 to 2034鈥�35. It aims to connect 20,600 habitations, specifically Majra-Tolas that ..
Next Story
CAQM Signs Pact to Cut Dust Pollution in Delhi-NCR
In a strategic move to tackle dust pollution in Delhi and the National Capital Region (NCR), the Commission for Air Quality Management (CAQM) has entered into a tripartite agreement with the CSIR-Central Road Research Institute (CRRI) and the School of Planning and Architecture (SPA). Signed on Tuesday, the Memorandum of Understanding (MoU) aims to implement a standardised urban road redevelopment framework across key NCR cities.The initiative will focus on paving and greening footpaths and sidewalks鈥攎easures considered vital for reducing road dust, a significant contributor to poor air qual..