NCRTC Installs 200-Tonne Steel Span at Barapullah Flyover
RAILWAYS & METRO RAIL

NCRTC Installs 200-Tonne Steel Span at Barapullah Flyover

The National Capital Region Transport Corporation (NCRTC) has completed the installation of a two hundred-tonne steel span over the Barapullah flyover, linking Sarai Kale Khan station with the upcoming Jangpura stabling yard on the Delhi-Ghaziabad-Meerut RRTS Corridor.

The steel span comprises four girders, each forty metres long and weighing fifty tonnes. The structure was installed in ten nights with support from the Public Works Department and Delhi Traffic Police to avoid major traffic disruption.

To manage the complex elevation and space constraints, a special two-stage lifting method was used. Initially, two cranes stationed on one side placed the girders on the flyover. In the second stage, two more cranes positioned on either side lifted the girders onto designated pillars.

NCRTC explained that such special spans are used in areas where regular pillar spacing is not feasible, such as over drains, flyovers or other infrastructure. Safety measures included coordination with Delhi Transco Limited, as a high-tension line passes above the site.

Trial runs have already begun on the 4.5-kilometre stretch between Sarai Kale Khan and New Ashok Nagar, with the full corridor expected to be operational by mid-2025.

Source:Hindustan Times

The National Capital Region Transport Corporation (NCRTC) has completed the installation of a two hundred-tonne steel span over the Barapullah flyover, linking Sarai Kale Khan station with the upcoming Jangpura stabling yard on the Delhi-Ghaziabad-Meerut RRTS Corridor.The steel span comprises four girders, each forty metres long and weighing fifty tonnes. The structure was installed in ten nights with support from the Public Works Department and Delhi Traffic Police to avoid major traffic disruption.To manage the complex elevation and space constraints, a special two-stage lifting method was used. Initially, two cranes stationed on one side placed the girders on the flyover. In the second stage, two more cranes positioned on either side lifted the girders onto designated pillars.NCRTC explained that such special spans are used in areas where regular pillar spacing is not feasible, such as over drains, flyovers or other infrastructure. Safety measures included coordination with Delhi Transco Limited, as a high-tension line passes above the site.Trial runs have already begun on the 4.5-kilometre stretch between Sarai Kale Khan and New Ashok Nagar, with the full corridor expected to be operational by mid-2025.Source:Hindustan Times

Next Story
Infrastructure Urban

Reliance, Diehl Advance Pact for Precision-Guided Munitions

Diehl Defence CEO Helmut Rauch and Reliance Group鈥檚 Founder Chairman Anil D. Ambani have held discussions to advance their ongoing strategic partnership focused on Guided and Terminally Guided Munitions (TGM), under a cooperation agreement originally signed in 2019.This collaboration underscores Diehl Defence鈥檚 long-term commitment to the Indian market and its support for the Indian Government鈥檚 Make in India initiative. The partnership鈥檚 current emphasis is on the urgent supply of the Vulcano 155mm Precision Guided Munition system to the Indian Armed Forces.Simultaneously, the 鈥淰ulc..

Next Story
Infrastructure Urban

Modis Navnirman to Migrate to Main Board, Merge Subsidiary

Modis Navnirman Limited has announced that its Board of Directors has approved a key strategic initiative involving migration from the BSE SME platform to the Main Board of both BSE and NSE, alongside a merger with its wholly owned subsidiary, Shree Modis Navnirman Private Limited.The move to the main boards marks a major milestone in the company鈥檚 growth trajectory, reflecting its consistent financial performance, robust corporate governance, and long-term commitment to value creation. This transition will grant the company access to a broader investor base, improve market participation, en..

Next Story
Infrastructure Urban

Global Capital Flows Remain Subdued, EMEA Leads in Q1 2025

The Bharat InvITs Association鈥檚 industry update for Q1 2025 shows subdued global capital flows, with investment volumes remaining at the lower end of the five-year range despite a late 2024 recovery. According to data from Colliers and MSCI Real Capital Analytics, activity in North America declined slightly, while EMEA maintained steady levels and emerged as the top region for investment in standing assets.The EMEA region now hosts seven of the top ten cross-border capital destinations for standing assets, pushing the United States鈥� share of global activity below 15 per cent. Meanwhile, in..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement