Pune metro finally completes elevated stretch on Corridor I
RAILWAYS & METRO RAIL

Pune metro finally completes elevated stretch on Corridor I

The elevation of a 12.064-km rail segment on the route from PCMC Station to Swargate Station of Pune Metro Corridor I was completed this week. The stretch from Pimpri Chinchwad Municipal Corporation Station to Range Hill Station is elevated and the rest of the route is underground.

The trial run of the metro train on the route from Phugewadi station to Civil Court station can now be conducted soon. After the trial, the route from Phugewadi station to Civil Court station will be opened for passengers.

A total of 3,934 segments were cast for the elevated track. As many as 451 spans were constructed through these segments and 12.064 km of elevated track was constructed.

Many hurdles were overcome to complete this elevated route. The biggest difficulty was getting the land from Harris Bridge to Khadki from the Army. After continuous follow-up with the Army, the metro authorities finally got land in July 2022.

With the launching of the last segment, the gap in viaduct route between Pimpri Chinchwad Municipal Corporation Station to Harris Bridge and Range Hill Station to Khadki is filled and the viaduct complete.

See also:
CMDA to develop 18 MRTS stations
Railways to spend Rs 900 bn on optimising freight movement


The elevation of a 12.064-km rail segment on the route from PCMC Station to Swargate Station of Pune Metro Corridor I was completed this week. The stretch from Pimpri Chinchwad Municipal Corporation Station to Range Hill Station is elevated and the rest of the route is underground. The trial run of the metro train on the route from Phugewadi station to Civil Court station can now be conducted soon. After the trial, the route from Phugewadi station to Civil Court station will be opened for passengers. A total of 3,934 segments were cast for the elevated track. As many as 451 spans were constructed through these segments and 12.064 km of elevated track was constructed. Many hurdles were overcome to complete this elevated route. The biggest difficulty was getting the land from Harris Bridge to Khadki from the Army. After continuous follow-up with the Army, the metro authorities finally got land in July 2022. With the launching of the last segment, the gap in viaduct route between Pimpri Chinchwad Municipal Corporation Station to Harris Bridge and Range Hill Station to Khadki is filled and the viaduct complete. See also: CMDA to develop 18 MRTS stationsRailways to spend Rs 900 bn on optimising freight movement

Next Story
Resources

Cushman & Wakefield Names Sona Aggarwal as APAC Retail Lead

Cushman & Wakefield, a global real estate services firm, has announced the appointment of Sona Aggarwal as Managing Director, Head of Retail Sales and Strategy, Asia Pacific. Based in Singapore, Sona joins at a pivotal time as the firm scales up its regional retail platform, aiming to deliver global expertise to clients across Asia Pacific (APAC) and beyond. With over 25 years of experience in global brand management and retail operations, Sona has led the launch and operations of more than 200 stores across APAC, managing cross-border teams of over 1,300 people. Her deep understandin..

Next Story
Technology

CommScope Launches CableGuide 360 and Enhanced FiberREACH Solutions

CommScope, a global leader in network connectivity, has introduced two new solutions under its SYSTIMAX庐 2.0 portfolio鈥攖he enhanced FiberREACH鈩� solution and the new CableGuide 360鈩� platform. These solutions aim to help enterprises extend power and connectivity to the network edge while simplifying high-density cable management. Previously known as the Powered Fiber Cable System (PFCS), FiberREACH builds on its legacy by integrating advanced hybrid-fibre cabling, increased power delivery, and chassis solutions. The upgraded system now supports up to 90W of Power over Ethernet (PoE) ..

Next Story
Real Estate

Lodha Buys Rs 5.67 Billion Transit Units in Mankhurd

Mumbai-based listed real estate developer Lodha Developers Limited has acquired 945 permanent transit camp (PTC) units measuring 339,000 square feet from Arihant Construction Company for Rs 5.67 billion. The transaction, registered on 3 June 2025, is part of Lodha鈥檚 obligations under the Slum Rehabilitation Authority (SRA) scheme related to its ongoing township project in Vikhroli.The acquired units in Mankhurd will be handed over to the SRA to secure development rights for free-sale construction under the Vikhroli project. The deal includes a stamp duty payment of Rs 340.2 million and regis..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement