Bullet Train: 190 km viaduct and 321 km of pier completed
05 Jul 2024
2 Min Read
CW Team
For the Ahmedabad-Mumbai bullet train project, the National High Speed Rail Corporation Limited (NHSRCL) has finished building 321 km of piers and 190 km of viaducts. Furthermore, eight of the twenty-four river bridges have had their bridge construction finished. When describing the project, NHSRCL representatives said that all civil contracts had been given out across Gujarat and Maharashtra. They affirmed that all land acquisitions in Maharashtra, Gujarat, and Dadra and Nagar Haveli (DNH) have been finished.
Besides the civil works, all depot and electrical contracts have also been awarded. The officials said that two state-of-the-art track slab manufacturing facilities in Surat and Anand are fully functional to support the track system.
The completion of the first mountain tunnel, spanning 350 meters near Zaroli Village in Valsad, was announced. The officials said that three steel bridges, measuring 70 meters, 100 meters, and 130 meters, have also been completed in Surat, Anand, and Vadodara, respectively.
Bridge works on eight out of the total 24 river bridges along the Bullet Train corridor, including those on the Par, Purna, Mindhola, Ambika, Auranga, Venganiya, Mohar, and Dhadhar rivers, have also been completed. The work on other major rivers, such as the Narmada, Tapti, Mahi, and Sabarmati, is in progress.
A 7 km undersea rail tunnel in Maharashtra is being worked on as part of a 21 km tunnel that would connect BKC and Shilphata. In Gujarat, 338 km of the 352 km of viaduct have had their foundations built, while 5,549 girders totaling 222 km have been cast. All eight Bullet Train Stations?Vapi, Bilimora, Surat, Bharuch, Anand, Vadodara, Ahmedabad, and Sabarmati?have completed their foundation construction.
Earthwork at the Sabarmati Depot is complete, and work is underway to lay the foundation for overhead equipment as well as construct the administrative structure and a number of buildings and workshops, according to NHSRCL officials.
For the Ahmedabad-Mumbai bullet train project, the National High Speed Rail Corporation Limited (NHSRCL) has finished building 321 km of piers and 190 km of viaducts. Furthermore, eight of the twenty-four river bridges have had their bridge construction finished. When describing the project, NHSRCL representatives said that all civil contracts had been given out across Gujarat and Maharashtra. They affirmed that all land acquisitions in Maharashtra, Gujarat, and Dadra and Nagar Haveli (DNH) have been finished.
Besides the civil works, all depot and electrical contracts have also been awarded. The officials said that two state-of-the-art track slab manufacturing facilities in Surat and Anand are fully functional to support the track system.
The completion of the first mountain tunnel, spanning 350 meters near Zaroli Village in Valsad, was announced. The officials said that three steel bridges, measuring 70 meters, 100 meters, and 130 meters, have also been completed in Surat, Anand, and Vadodara, respectively.
Bridge works on eight out of the total 24 river bridges along the Bullet Train corridor, including those on the Par, Purna, Mindhola, Ambika, Auranga, Venganiya, Mohar, and Dhadhar rivers, have also been completed. The work on other major rivers, such as the Narmada, Tapti, Mahi, and Sabarmati, is in progress.
A 7 km undersea rail tunnel in Maharashtra is being worked on as part of a 21 km tunnel that would connect BKC and Shilphata. In Gujarat, 338 km of the 352 km of viaduct have had their foundations built, while 5,549 girders totaling 222 km have been cast. All eight Bullet Train Stations?Vapi, Bilimora, Surat, Bharuch, Anand, Vadodara, Ahmedabad, and Sabarmati?have completed their foundation construction.
Earthwork at the Sabarmati Depot is complete, and work is underway to lay the foundation for overhead equipment as well as construct the administrative structure and a number of buildings and workshops, according to NHSRCL officials.
Next Story
Sterling Unveils Premium Retreat Near Lansdowne at Vanvasa Resort
Sterling Holiday Resorts has launched Sterling Vanvasa, its latest premium hideaway located near Lansdowne, Uttarakhand. Set amidst 30 acres of forested hillside, this offbeat destination is designed for travellers seeking tranquillity, nature, and a break from urban stress. It marks Sterling鈥檚 eighth resort in the state, strengthening its position in curating India鈥檚 most serene holiday escapes. Situated beyond Juee village at an altitude of over 3,200 feet, the retreat offers panoramic views of the Garhwal Himalayas, lush pine and sal forests, and the distant Ramganga river. Far fro..
Next Story
REC Wins ASSOCHAM CSR Award for Healthcare Support Initiatives
REC, a Maharatna Central Public Sector Undertaking (CPSU) and leading non-banking financial company (NBFC) under the Ministry of Power, Government of India, has received the ASSOCHAM CSR and Sustainability Award 2024 for 鈥楨xcellence in Providing Support to Healthcare鈥�. The award was presented during the 6th ASSOCHAM CSR and Sustainability Conference and Awards held in Hyderabad. Shri Anjan Lahiri, Senior General Manager and Head of Department (REC Foundation), received the honour on behalf of REC from the Hon鈥檅le Deputy Chief Minister of Telangana, Shri Mallu Bhatti Vikramarka. ..
Next Story
Essensai067 to Launch Sustainable Adventure Park for Children in July
Essensai067, the sustainable, community-first retail enclave in Whitefield, is set to open a state-of-the-art Adventure Park for children under 12 this July. Designed to foster physical activity, imagination, and social connection, the park aligns with Essensai067鈥檚 philosophy of creating meaningful, inclusive spaces. Spread across 5.16 acres of heritage land, Essensai067 integrates food, fashion, art, and music with wellness and community engagement. The Adventure Park reinforces this vision by offering a nature-inspired play environment, aimed at reducing children鈥檚 screen time and ..